Sunday, September 9, 2012

Underground


September 4, 2012
Weather;                                                                                                                                                                                             
98 degrees feels 112    
 44 % humidity   
  sun / cloudy

                             

      

Tuesday Got to the job, meet with the superintendent and receive the correct set of plans. Check the floor plans sub- panel measurements. Laid out the walls for the sub-panels, mark out trenches. Receive 90% of the pipe order.


 
                      

September 5,2012                                                               


Weather;                                                                                                                                                            
105 degrees                                                                                                                                                      
44% Humidity
 Cloudy /Sun
 


Wednesday


J H Thomson; Dug Out the Electrical 10x10 by 3’ deep and trench to the  Sub-panel in  the rear of the building . Operator started at 7:30 am, 1Hr Lunch, Stop at 2:00pm. @ 230’

I went over  the idea’s  with mike on the Generator Placement, looking the plans the generator  was to close to the building per code and we kind of came up with  a placement of the pad. He is working with the architect and fire department for correct placement. For now we will pipe the run out  towards the trans former  so can we get out of the way of the lint tank that is arriving Monday September 10, 2012.
Mike also told me that the tv Run we are installing one 2" conduit from the phone room to the north east corner of the property. @ 400’ no telephone conduit is needed.

Jr Spotted the Excavator thru-out the trenching for depth at the footings and the plumber’s main line.
We piped the trenches for the sub-panels, lighting contactor, generator annunciation and TV run.
We received the second half of pipe order which the supplier had to go the LA branch to pick up the 24’’ 90’s.   We received 40’ of 3” pipe and 3 of 24’’x3 90’s.





September 6, 2012 Thursday                                                                                                     
Weather;
106 degrees
22% Humidity
Sun / windy

J h Thomson; Dig trench for the generator   1 ½ hrs @ 50’ 

Finish piping sub-feed Trenches,  re-pulled layout strings, Set sub-panel risers, Piped the generator run  and started back-fill trenches which inspected at 2pm. 



September 7, 2012 Friday

Weather:
104 degrees
28% humidity
Sunny

Finish piping Electrical room, backfill, compact trenches and electrical room.
Pick up 6 of 2 ½ couplings and 20’ of pipe 
Pick one 10x12 to use as bridges over open footing so could back fill with the bobcat.



                                                                                                               












                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                       