Wednesday, October 24, 2012

Job status

       Oct 24 2012

  • 2/3 of bldg framing are set all the way to the back dining room
  • Underground crew has dug out all 10 of the light pole bases and have set 5 Saunatube on the west side of the bldg and are ready for rebar that we have trenched to. We will be trenching to the remaining pole light bases Thursday 10/25/12. Rebar setting and grounding on Friday 10/26/12.
 Oct 26,2012
  • Finished trenching to all the light pole bases.
  • The underground crew are digging the last two bases, and we be setting cages, grounds,and anchor bolts on Monday. They were not ready on Friday for grounding.


Oct 29, 2012
·         Went to White cap and pickup the 3/4 x 18” anchor bolts.
·         Help set the cages, grounded, and set anchor bolts. Clean the trenches around the light pole base and install the conduits into the bases.
Oct. 30, 2012
·         While waiting for inspection on the light pole base. I had taken the extra time to do some boxing in the corridors.  
·         After the 9:30 am inspection, I had gone to the nearest rental yard and ordered a skid steer for back fill. Back fill and graded all the trenches, clean up 80% of the dirt that had spilled over into the parking lot from the trencher and from the light bases holes that they dug.
  • Loaded 164 can light fixture into the container.
Oct. 31, 2012
·         Rec’v the alien material order from desert electric supply and loaded it into the container.
·         Had the skid steer pick up and went over to rental yard to finalize the rental paper work, (ie.pay) for it.
·         Box some more of the core in the building.
·         Set up the delivery for the switch gear.



Nov. 1, 2012

·         Box out the electrical room area; prep the electrical room for the switch gear.
  • Rec’v 62 of the “c” can light fixtures. Loaded can light fixture into the container.
·         Rec’v the switch gear.

Nov.2, 2012
·         Loaded the switch gear into the electrical room, waiting on the local AHJ to approve the wall for sheet rock.
·         Layout the Mechanical room with the plumber and boxed it out.
·         Friday clean up.


Nov. 5, 2012
·         Got Approval on the Electrical room wall, will start pre rock on Tuesday.
·         Pre drill the sub panels, adjusted conduits; will be pre rock on   Tuesday.
·         Cut in the Exterior boxes, work on boxing the core.

Nov.6, 2012
·         Could not start pre rock today the framers were rolling trusses today over the kitchen and mechanical rooms.
·         Started boxing the rooms.
·         Box out the front core area.
·         Started installing the fire rated.
·         Help Jr lay out the ceiling boxes in the rooms.
·          
Nov .7 2012
·         Took mike to the home depot and pick up the sheet rock material.
·         Pre rock the electrical room.
·         Drill out the four 2” holes above all the sub-panels.
·         Finish boxing the rooms 1-15
Nov.8, 2012
·         Pre rock the sub –panel s and install panel can 1,2,3,4,5,8
·         Started setting the Switch gear and will finish Friday morning
·         Started boxing room 34- 46
Nov 9, 2012
·         Installed the front soffit can lights
·         Walk the building with jay
·         Set the switch gear place, bolted the buses together.
·         Finish boxing  rooms 34-46
Nov 12, 2012
·         Bolted the switchgear to the floor and torque the buses
·         Installed a S/o cord though the kitchen conduit for temp power
·         Clean up the electrical room
·         Started boxing rooms 16-33
·         Boxed the laundry room area


Nov 13, 2012

·         Meet with the inspector for the temporary green tag
·         Installed  soffit can lights pushing the framer to finish
·         Double check the corridors for missing boxes and drill for pre-wire
·         Meet with the inspector for the temporary green tag on the switch gear
·         Finish boxing rooms 16-33
Nov 14, 2012

·         Installed  soffit can lights pushing the framer to finish
·         Drilled rooms  1-15
·         Remove sheet rock from the back of  6,7, kitchen panels and finish install them
·         Boxed the back activity and living room where they final finish the trusses
·         Received 3000 feet of 12-2mc  and started pre-wire the corridors
·         Meet with IID power to mandrel the second dairies, transformer and power is schedule for the first week in December

Nov 15, 2012

·         Pre-wire core and soffit cans lights
·         Boxes and pipe all the misc ¾ conduits
·         Did not receive the second order of 4000 12-2 mc, we need to order the wire two days ahead of time. Thursday order out of Palm Springs will be deliver Monday.
·         Install some of fire rated cans in the common areas.
·         The HVACs crew finally  showed up today, and we will  pre wire mechanical  rooms Monday

Nov 16, 2012

·         Start make-up on the Exterior Soffit cans
·         Received  4000, feet  of 12-2mc
·         Finish corridor Pre-wire for the exception of the back activity corridor lights, where the framers are installing the cat walk, will finish Tuesday am.
·         Monday plan of attract is to wire mechanical rooms and pull core home runs


2 comments:

  1. This comment has been removed by the author.

    ReplyDelete
  2. Mainly I am commenting so I get a gmail responce whenever you enter a update. In the report include the following:
    What Ron worked on that day and what he will do tomorrow
    What Jr worked on that day and what he will do tomorrow
    What Michael worked on that day and what he will do tomorrow
    What other subs are on site and what they are working on
    What materials have arrived
    Any requests from Mike H